When a Capital Refurbishment Project Fails

September 1, 2017

By Lisa Ciota

September 2017

In the late 1990s, a senior leader at the company’s largest customer said, “We like the industrial material you produce and your operating process. Can you build a new facility and operate it just for us? We’ll lease you land right on our property and you can ship your materials to us on a conveyor belt.” At the time, the company was a small, scrappy business eager to prove the viability of its innovative and environmentally sound operating process that met Environmental Protection Agency (EPA) standards.

Management eagerly agreed and retained a well-known industrial construction firm to build the facility. Now, management was in a hurry – so when the construction firm proposed using a new method to lay the pilings of the plant’s foundation, management agreed despite the deep misgivings of its own engineering staff. The engineers were right. A few years after the plant’s start-up, the facility began to buckle and settle. This caused operational difficulties and production shortfalls. The rising operating costs burned a hole in the company’s P&L. In comparison, the company’s other four production facilities ran like Swiss watches, consistently delivering on production and operating targets and generating strong cash flow.

When the plant was just 13 years old, a new management team commissioned an engineering study to identify a long-term solution to solve the plant’s problems and enable it to achieve an expected lifespan of 50-60 years. Based on the study’s results, the company announced an $85 million capital refurbishment effort. Ultimately, this project required more than two years to complete, overran the budget by 50% (to $125 million) and did not materially improve production levels or lower operating costs.

As a result, the company’s chief operating officer and VP of manufacturing operations were forced to resign two weeks before quarter end. In the resignation announcement, the company couldn’t comment on quarterly results but appropriately positioned the resignations as an opportunity to streamline management and strengthen its focus on operations excellence.

Quarter-end came soon enough and results were not good. Given the shortfall’s magnitude, following the usual practice of releasing quarterly production volumes one week after quarter end would lead to questions that couldn’t be answered until earnings were issued two weeks later, creating a prolonged period of uncertainty. Accordingly, the company accelerated its earnings release by two weeks in lieu of separately announcing quarterly production volumes.

Investor reaction was swift and negative. Management’s credibility was damaged given the perceived failure of the capital improvement effort. Even worse, the company could not definitively announce a solution or costs since it was still testing new approaches to fixing the plant’s problems. Compounding the situation, customers and competitors were idling or shuttering plants due to deteriorating industry conditions. The stock dropped more than 15% on the day of earnings and nearly another 20% over the next week.

To address investor concerns, company management conducted a series of calls with top investors and certain activists immediately after earnings. The following week, the IRO and CEO went on the road to meet key investors. These actions helped reinforce the company’s commitment to transparency and kept the lines of communication open as it dealt with activists agitating for change at the company.